What Is PMC (Preventive Maintenance Compliance)?

PM compliance is the percentage of scheduled preventive maintenance tasks completed on time within a given period.

Back to the glossary

A preventive maintenance programme only works if the tasks are actually done. PM compliance measures how well the schedule is being followed.

PM Compliance Formula

PM compliance = (PM work orders completed on time / PM work orders scheduled) × 100

For example, if 180 of 200 scheduled PMs were completed on time this month, PM compliance is 90%.

Defining "On Time"

Organisations usually allow a tolerance window, such as completing a monthly PM within a few days of its due date. Defining this clearly keeps the KPI fair and consistent.

Targets

Many organisations target 90% or more, with critical and safety related PMs expected to be completed on time without exception.

Why PM Compliance Drops

  • Not enough labour or competing emergency work
  • Equipment not released by production
  • Missing spare parts
  • Too many low value PM tasks

Improving PM Compliance

Review and remove low value PMs, schedule PMs with production in advance, ensure parts are available and track overdue PMs weekly. Critical PMs should be clearly flagged in your CMMS.

See how Oriens puts PMC into practice.

Explore Oriens Maintenance Planning

Related Terms

Ready to modernise your asset management?

See how Oriens EAM and Oriens HSE bring maintenance, assets and safety together on one platform.

Request a Free Demo