What Is PMP (Planned Maintenance Percentage)?

Planned maintenance percentage is the share of maintenance hours spent on planned work rather than unplanned, reactive work.

Back to the glossary

Planned maintenance percentage (PMP) shows how proactive a maintenance organisation is. The more work is planned, the less time is lost to emergencies.

PMP Formula

PMP = (Planned maintenance hours / Total maintenance hours) × 100

For example, if 340 of 400 maintenance hours in a month were planned, PMP is 85%.

What Counts as Planned

Planned work typically includes preventive maintenance, predictive maintenance and corrective work that was identified in advance and planned before execution. Emergency breakdown repairs are unplanned.

Benchmarks

Many reliability practitioners aim for a PMP of 85% or higher. Organisations dominated by reactive maintenance may be well below 50%.

How to Improve PMP

  • Build an effective preventive and predictive maintenance programme
  • Report defects early, so they can be planned before they become failures
  • Introduce formal planning and scheduling
  • Analyse and eliminate repeat failures

Tracking work types consistently on every work order is essential for an accurate PMP.

See how Oriens puts PMP into practice.

Try the Maintenance Calculators

Related Terms

Ready to modernise your asset management?

See how Oriens EAM and Oriens HSE bring maintenance, assets and safety together on one platform.

Request a Free Demo